C2-Lomié
- Construction of a new raw water intake, installation of raw water pumps and laying of a 100m HDPE OD 160 raw water main
- Construction of a new water treatment plant (60 m³/h) equipped with a concrete decanter and a self cleaning filter.
- Construction of a 130 m³ concrete tank
- Construction of the pump room and installation of the treated water pumps
- Laying of a 3,400 m HDPE OD 160 treated water main
- Construction of a 500 m³ reservoir
- Construction of a 3,200 m MV electrical line and installation of a160 kVA transformer
- Densification of the distribution network with laying of 6,150 m HDPE OD 160 and 1,850 m HDPE OD 200 pipes
- Construction of the operator’s office.