C2-Mbé
- Rehabilitation and upgrade of the boreholes (20 m³/h)
- Removal of the lamellar clarifier and filter and installation of a new filter
- Rehabilitation of the treated water pumping station
- Reinstallation of the disinfection unit
- Reinstallation of the control panel, the local cabinets, tertiary and the commissioning
- Reinstallation of the existing generator
- Rehabilitation, cleaning and disinfection of the elevated tank
- Reinstallation of the damaged part of the treated water main
- Densification of the distribution network with laying of 8,000m HDPE OD 90 pipes.