C2-Yoko

admin/uploads/blog/4861efbc4168abb0a07570e92a49d2a2.jpgdbef4ac3e69ec9db9b62da97e9c5731b.jpg
admin/uploads/blog/4861efbc4168abb0a07570e92a49d2a2.jpg

C2-Yoko

  • Construction and equipment of 4 boreholes (7 m³/h each).
  • Densification of the distribution network with laying of 11 km HDPE pipes (OD 110 and OD 90).
  • Laying of a 3,200 m HDPE OD 160 treated water main.
  • Construction of the treatment (disinfection) unit, with hydromechanical and electrical connections.
  • Construction of a new 200 m³ storage tank in reinforced concrete.
  • Construction of a 4 km MV electrical line and installation of a 100 kVA transformer.
  • Construction of technical buildings.
  • Construction of the operator’s office.

  • Date Started: 2019-02-01
  • Date Completed:Ongoing Project
  • Location: Cameroon
  • Category: Construction
  • Tag: Construction