T2-Tokombéré
- Construction of 1 borehole (30 m3/h)
- Construction of a chlorination station
- Laying of a 9 km of HDPE delivery main pipe OD 160 – SDR 11
- Construction of a 200 m3 elevated storage tank (15 + 5 m)
- Laying of a 24 km HDPE distribution network
- Construction of an operator’s office for billing and revenue collection
- Connection to the power grid.